Projects / A kitchen in nine days
A kitchen, template to install, in nine days.
A remodeler had nine working days between cabinets and the owners’ return. The house was built in 1948 and no wall in it was straight.

Job facts
- Location
- Sam Hughes, Tucson
- Client
- Remodeling contractor
- Material
- Honed quartzite, 3 cm, two slabs
- Scope
- Perimeter counters, 9-foot waterfall island, full-height backsplash behind the range
- Schedule
- Template to walkthrough: 9 working days
The problem
The homeowners were away for three weeks and the contractor had promised a working kitchen when they came back. Cabinets went in late, which left nine working days for stone, plumbing and paint.
Our standard is seven to ten days for the stone alone, so there was no room for a second trip.
Constraints
- The back wall was three quarters of an inch out of straight over ten feet. A counter cut square would leave a tapered gap no caulk would hide.
- The owners wanted the island’s veining to run down the waterfall end without a break.
- Both slabs came from the same block, and there was no third. A wrong cut meant a six-week reorder.

What the crew did
- The template tech measured the day the last cabinet was leveled, and scanned the back wall every six inches instead of every two feet.
- We laid the template on photos of both slabs that afternoon and sent the contractor two layouts. He chose the one that kept the strongest vein on the island.
- The saw cut the backsplash to the wall’s actual curve. The waterfall miter was cut from one continuous piece so the veins line up across the corner.
- Two crews installed on day eight. The plumber connected the sink the next morning.
The result
The kitchen was finished a day before the owners landed. The gap at the back wall is a consistent sixteenth of an inch, top to bottom.
The contractor has sent us eleven kitchens since.