City of Calder Springs · Public Works
Tamarisk RoadImprovement Project
Menu: Map and phases

You are here: Tamarisk Road / Map and phases

Map and phases

The work moves from west to east in three phases, so only one section of the road is under construction at a time.

The short version

  • Phase 1, Depot Street to Canal Street: January to August 2027.
  • Phase 2, Canal Street to Quarry Road: September 2027 to May 2028.
  • Phase 3, Quarry Road to Fairground Drive: June 2028 to January 2029.
Choose a phase

The map shows the phase you choose and its detour. The same details are in the table below the map.

NHarlan Avenue (detour)Phase 1January to August 2027Phase 2September 2027 to May 2028Phase 3June 2028 to January 2029Tamarisk RoadEastside Community CenterMill Street washTamarisk ElementaryCounty FairgroundsDepot StreetCanal StreetMill StreetOrchard LaneQuarry RoadFairground Drive
  • Phase under construction
  • Detour route
  • Planned closure
  • Landmark

Phase 1

Depot Street to Canal Street

Dates
January to August 2027
What gets built
  • Move water and power lines
  • Build the new storm drain
  • Rebuild the road with a center turn lane
  • Add sidewalks, bike lanes and streetlights
  • New signal and crossing at Canal Street
Planned closures
Depot Street intersection closed two weekends in February 2027. Canal Street intersection closed five nights in June 2027.
Detour
Harlan Avenue, one block north.

Phase 2

Canal Street to Quarry Road

Dates
September 2027 to May 2028
What gets built
  • Replace the low crossing at the Mill Street wash with a bridge
  • Rebuild the road with a center turn lane
  • Add sidewalks, bike lanes and streetlights
  • New crosswalk with flashing beacon at Tamarisk Elementary
  • Two new bus stop shelters for Route 7
Planned closures
Tamarisk Road closed between Mill Street and Orchard Lane for about 14 weeks, November 2027 to February 2028, while the bridge is built. Homes and businesses on that block stay reachable.
Detour
Harlan Avenue between Canal Street and Quarry Road.

Phase 3

Quarry Road to Fairground Drive

Dates
June 2028 to January 2029
What gets built
  • Rebuild the road with a center turn lane
  • Add sidewalks, bike lanes and streetlights
  • New signal at Fairground Drive
  • Final paving and striping for the whole road
Planned closures
Fairground Drive intersection closed five nights in October 2028. No lane closures during the county fair, September 14 to 24, 2028.
Detour
Harlan Avenue, one block north.

Timeline

  1. 2024Traffic and drainage studiesDone
  2. 2025Preliminary design and first round of public meetingsDone
  3. Fall 2026Final design and second round of public meetingsNow
  4. January 2027Phase 1 construction starts
  5. September 2027Phase 2 construction starts
  6. June 2028Phase 3 construction starts
  7. Early 2029Landscaping finished and the project closes

Dates can move with weather and utility work. Any change is posted here and sent to the email list at least seven days ahead.

Page updated November 5, 2026